The project marks the start of a strategic partnership between SMA Altenso and RheinEnergie. While our partner RheinEnergie will be responsible for operating and marketing the facility, Altenso will take on development, constructions and maintenance services. Designed for an output of 24.5 MW and a usable capacity of 64 MWh, the large-scale battery park is expected to be commissioned in early 2026.
Project Figures
Power
24.5 MW
Battery Capacity
64 MWh
Role
Project Developer and EPC
Components
8 x MVPS 3800
Monitoring
SMA Power Plant Manager
Monitoring System
Application
Frequency response services
SMA System Technology
Our power conversion units and battery containers are manufactured in a serial mass production in Kassel (Germany). We keep highest production standards and deliver worldwide even to very remote and secluded locations.
20 foot Medium Voltage Power Station (MVPS)
containing SMA Sunny Central Storage inverter technology